Project background:

2010: Siemens is awarded the project to modernize Arcelor Mittal’s B furnace.

December 2010: Siemens and Hexa Ingenieros become partners in the execution of Arcelor Mittal Project

January 2011: Programming work is carried out at Siemens in Tres Cantos (Madrid), Spain

September 2011: End of FAT testing at Arcelor Mittal premises in Gijón, Spain.

July 2012: Control system commissioning is carried out.

September 2012: End of control system commissioning.

January 2013: After solving several problems unrelated to project B Arcelor Mittal furnace begins operations.

Technology:
Control System Siemens Simatic PCS7 version 7.1